Want a new deck? Before you pay for a design, ask one question first. Could Erina Creek flooding change what you can build?
Why this matters in Erina
- Erina is one of the Central Coast suburbs in the Erina Creek catchment.
- Central Coast Council’s flood study from 2015 found that Erina had the second-highest number of houses flooded in more common floods.
The creek starts in steep land that is mostly covered in plants. Further down, the land is low and flat. There, flood levels are also affected by Brisbane Water.
This doesn’t mean your block is flood affected. But if it is, Council’s flood controls could affect your deck’s:
- height;
- framing;
- fill;
- place on the block.
On Erina jobs, we ask about flood controls at our first site visit. It’s much easier to plan around them before a design is drawn.
How Could Erina Creek Flood Controls Affect a New Deck?
It depends on your lot. If Central Coast Council’s flood controls apply to your Erina block, they could affect your deck in these ways.
| Area | What the controls say |
|---|---|
| Whether controls apply | Your Section 10.7 Planning Certificate shows if your block is a flood control lot. |
| Framing and materials | Erina is covered by the former Gosford area controls. Building parts below the Flood Planning Level must stay strong when wet, be easy to clean after a flood, and stand up to floodwater, debris and buoyancy (water pushing up). This could apply to a deck’s subframe. |
| Fill | Filling the ground in the Flood Planning Area needs Council approval. This includes cut and fill. |
| Creek setback | On major creeks without an approved waterway design, a building must be at least 6 m back from the top of each bank. |
| Floodway fencing | In a floodway, only permeable, open-type or safety fences approved by Council are allowed. |
The Flood Planning Level is the 1-in-100 chance flood level plus an extra safety margin.
Check first:
Ask Council or a certifier how each control applies to your deck.
Why Erina Creek Matters When You’re Planning a Deck
Erina Creek flows into Brisbane Water. Here are the key facts about the creek and the land around it.
The catchment
- It covers about 32 km² before the creek meets Brisbane Water.
- It covers all or part of Matcham, Erina Heights, Holgate, Mount Elliot, Erina, Springfield, Green Point and East Gosford.
The land
| Part of the catchment | What the land is like |
|---|---|
| Upper catchment | Fairly steep and mostly covered in plants |
| Lower catchment | Mostly low and flat. Flood levels here are affected by Brisbane Water levels. |
The flood history
Central Coast Council adopted its Erina Creek Floodplain Risk Management Study and Plan in 2015. The study found:
- big floods in the catchment several times since the 1970s;
- the most recent big flood was in June 2007;
- in more common floods, East Gosford had the most houses flooded, and Erina came next.
That’s why it pays to check your flood status early when you plan a deck in Erina.
Quick facts: Erina Creek
- Catchment size: about 32 km² to Brisbane Water
- Most recent big flood in the study: June 2007
- Study: Erina Creek Floodplain Risk Management Study and Plan, 2015
Step One: Find Out Whether Your Block Is Flood Affected
A flood control lot is a property that Central Coast Council’s flood controls apply to. Before you plan your deck, find out if your Erina block is one.
Three ways to check
| Where to check | What it tells you |
|---|---|
| 1. Section 10.7 Planning Certificate | Whether your property is a flood control lot |
| 2. Flood Information Certificate | More flood details for your property. Standard: 15 business days. Urgent: 3 business days. |
| 3. Council’s online mapping tool | Where the Flood Planning Area is |
What is the Flood Planning Level?
It is the 1-in-100 chance flood level plus an extra safety margin. This margin is called freeboard.
Our tip
If you already have your Section 10.7 certificate, we’ll ask to see it on our first visit. When flood information comes up after a design is drawn, the design sometimes has to change. We’d rather know at the start.
To learn more about how planning certificates and flood checks work for decks, see our Avoca Beach guide.
Got your certificate? Our team can talk you through what it means for planning a deck for your Erina home.
What Floodplain Controls Could Mean for Your Deck
If your Erina block is a flood control lot, some of Central Coast Council’s flood controls may affect your deck. Look closely if your block is on the low, flat land of the lower Erina Creek catchment.
Erina is in the former Gosford area. So the controls to read are the former Gosford area controls in Chapter 3.1 of the Central Coast DCP.
Keep in mind:
These controls don’t name decks in every case. Treat each one below as something that may apply. Then check it with Council or a certifier.
Height and the Flood Planning Level
- The control: In the former Gosford area, habitable floor levels for new structures must be above the Flood Planning Level.
- What’s not clear: Whether a deck counts as a habitable floor.
- What to ask: Does my deck need to meet the Flood Planning Level?
Framing and Materials Below the Flood Planning Level
Building parts below the Flood Planning Level must:
- stay strong and durable when wet;
- be easy to clean after a flood;
- stand up to floodwater, debris and buoyancy (water pushing up).
These rules could apply to a deck’s subframe. Check how they apply before you choose your framing and materials.
How we handle it
When a block has flood controls, we don’t lock in subframe or footing details until we know what Council or the certifier needs for that lot. We plan the framing around those needs, not after.
Fill and Levelling Under the Deck
- The control: Filling in the Flood Planning Area needs Council approval. This includes cut and fill.
- What to do: If your deck design needs fill to level the ground, raise this early.
Siting Near Erina Creek
- The control: On major creeks without an approved waterway design, the minimum setback is 6 m on each side, measured from the top of the natural bank.
- What’s not clear: The DCP applies this to “a building”.
- What to ask: If you plan to build near Erina Creek, does this setback apply to my deck?
Screens, Balustrades and Fencing in a Floodway
- The control: In a floodway, fencing is not allowed unless it is a permeable, open-type or safety fence approved by Council.
- Who it affects: Only lots in a floodway.
- What to ask: If part of my lot is in a floodway, does this limit affect deck balustrades or privacy screens?
Summary
| Control | What the DCP says | Question to ask about your deck |
|---|---|---|
| Flood Planning Level | Habitable floor levels for new structures must be above the Flood Planning Level (former Gosford area). | Does my deck count as a habitable floor? Must it meet the Flood Planning Level? |
| Parts below the Flood Planning Level | Parts below the Flood Planning Level must stay strong when wet, be easy to clean after a flood, and stand up to floodwater, debris and buoyancy. | Do these rules apply to my deck’s subframe? |
| Fill | Filling in the Flood Planning Area, including cut and fill, needs Council approval. | Will my deck need fill or levelling? |
| Creek setback | On major creeks without an approved waterway design, a building must be at least 6 m from the top of the natural bank on each side. | Does this setback apply to my deck? |
| Floodway fencing | Only permeable, open-type or safety fences approved by Council are allowed in a floodway. | Is my lot in a floodway? Does this limit apply to balustrades or screens? |
Once you know which controls apply, you can plan a custom deck design around site constraints.
Raised and Pole Homes Along Erina Creek: Matching a Deck to a High Floor
Raising houses has been widely used along Erina Creek in the past.
From Council’s 2015 study
- The study supports house raising for applicable buildings.
- It mentions pole homes on Chetwynd Road.
Is your Erina home’s floor well above the ground? Then a deck built to meet that floor would be an elevated deck. That can change which approval you need.
The 1 m height limit
| Rule | What it means for you |
|---|---|
| Under NSW exempt development rules, a deck floor can be no more than 1 m above existing ground level. | If your deck must meet a floor higher than 1 m, it would not meet this exempt height limit. |
If your floor is more than 1 m above the ground…
A deck built to meet it would not meet the 1 m exempt height limit. Ask Council or a certifier which approval pathway applies before you start your design.
What we plan for first
When we build a deck off a raised or pole home, access is usually the first thing we plan around. These all affect the layout:
- stairs;
- landings;
- the drop from the floor to the ground.
We work these out early with the client.
Does your deck need to step down from a high floor? You may want to look at elevated deck design or multi-level decks.
Questions to Settle Before You Commission a Deck Design
Before you lock in a deck design for your Erina home, answer these questions.
| Question | Where to find the answer |
|---|---|
| Is my block a flood control lot? | Your Section 10.7 Planning Certificate |
| What is the Flood Planning Level for my lot? | A Flood Information Certificate from Central Coast Council |
| Is any part of my block in a floodway? | Council or a certifier |
| How far will my deck be from the top of the Erina Creek bank? | Your deck plans |
| Will my deck need fill or levelling? | Your deck plans |
| Is my home’s floor more than 1 m above the ground? | Measure from the floor to the ground |
Last step:
Ask Council or a certifier how each former Gosford area control applies to your deck.